Fountain View Recreation Center – May 2013 Updates
Recent changes to the Fountain View Recreation Center include the installation of the Fitness Service Desk, fitness changing room lockers, and tiling of the swimming >>>
Fountain View Recreation Center – March 2013 Updates
Construction on the Fountain View Recreation Center is rapidly progressing. The concrete for the indoor swimming pool has been poured, the lighting and retractable basketball hoops >>>
Recreation Center – February 2013 Update
Carol Stream Park District staff and board members were able to tour the construction site in early February. Here are a few photos of the >>>
Recreation Center Update – Jan 2013
Updates over the past couple of months include the installation of glass is in on the south and west walls of the gym and almost >>>
Recreation Center Update – Nov 2012
The Fountain View Recreation Center is being to take shape. Workers currently on site include masonary, electrical and plumbing crews, work is continuing on the >>>
Recreation Center Update – October 2012
Ninty percent of the steel framework for the recreation center has now been installed. In early November work will begin on installing the gym roof >>>
Kuhn Road Bike Path Officially Open
Grab your bike, skates, stroller or walking shoes – The Kuhn-Ravanesi Trail was officially opened on Sunday Sept 23. The Village of Carol Stream and >>>
Governor Quinn Signs Bill To Improve Recreation in Carol Stream
Governor Pat Quinn visited Carol Stream on Monday, August 28 to sign a new law allowing the Carol Stream Park District to complete several new >>>
Red Hawk Trail Ribbon Cutting Set for Sept 23
The final one mile stretch of trail that links Carol Stream with the Great Western Trail was completed in August and will be officially opened >>>
Parks & Trails – August 2012 Update
Work is nearing completion on the final sections of trail that will link Carol Stream with the Great Western Trail. A short section of trail >>>